What Should Be Included in a Fire Rebuild Contract: A California Homeowner's Clause-by-Clause Review Guide

A fire rebuild contract should be written, specific, and cover every term that affects your money, your schedule, and the quality of work behind your walls. At minimum, it should identify the contractor by legal name and license number, describe the work and materials in detail, state a fixed price and payment schedule, name who pulls permits, set start and completion dates, explain how changes are handled in writing, spell out warranty terms, and include the required mechanics lien warning.
That is the short answer. The harder question — the one most homeowners are actually trying to solve — is whether the specific contract or proposal in front of you is clear enough, complete enough, and fair enough to sign. This guide walks through every major contract element, explains why it matters in plain English, tells you what to look for, and identifies who can verify each item: the California Contractors State License Board (CSLB), your insurer, your building department, an attorney, or a licensed architect or engineer.
This is an educational guide for homeowners in Altadena, Pacific Palisades, and other wildfire-affected areas in California. It is not a legal template, not legal advice, and not a substitute for attorney review. Requirements vary by property, jurisdiction, insurance policy, and project.
Why California Wildfire Rebuilds Follow Different Contract Rules
Before reviewing individual clauses, understand one important distinction. According to the CSLB's Disaster Help Center, rebuilding a home after a wildfire or other declared disaster is treated as home improvement, not new construction. That means home improvement contract and payment rules apply — even for a total-loss rebuild, and even for ADUs on the same property.
Two consequences matter immediately:
- Fixed-price contracts only. CSLB says contractors must use a fixed-price contract for disaster-related home improvement work. Time-and-materials and cost-plus contracts are not allowed for this work. (CSLB Disaster Help Center; CSLB contract and payment sheet, form 13P-106/0926)
- Payment caps. CSLB says the down payment cannot exceed $1,000 or 10 percent of the contract price, whichever is less. Progress payments must be listed in the contract and cannot exceed the value of work completed or materials delivered. There are no exceptions for special-order materials. (CSLB "Terms of Agreement" consumer guide, form 13P-045/1024)
Important: These statements reflect current CSLB guidance at the time of research. The underlying statutes should be confirmed on leginfo.legislature.ca.gov before you rely on specific numbers. Whether your project qualifies as a declared-disaster rebuild is a question for CSLB or an attorney. A small number of licensees with a blanket performance and payment bond on file with CSLB may be exempt from certain payment limits — ask your contractor and verify with CSLB if this comes up.
Clause-by-Clause Contract Review Table
Use this table to review a contract or proposal you have received, or to compare what two proposals cover. Each row names a contract element, explains why it matters, describes what to look for, identifies who verifies it, and notes the source.
| Contract Element | Why It Matters | What to Look For or Ask For | Who Verifies | Source |
|---|---|---|---|---|
| Contractor identity and license | Confirms you are contracting with a legal entity that is properly licensed and can be held accountable. Protects your ability to file a complaint or pursue a claim if something goes wrong. | Legal business name, physical address, phone number, CSLB license number and classification. CSLB's contract and payment sheet says a Class B (General Building) license is required for a home rebuild after a wildfire. Ask to see the pocket license and photo ID. Run the license number through CSLB's online License Check tool to confirm it is active and in good standing, and to check for complaints, bond status, and workers' comp coverage. | CSLB License Check tool | CSLB Disaster Help Center; CSLB contract and payment sheet (form 13P-106/0926); CSLB "Terms of Agreement" guide (form 13P-045/1024) |
| Workers' comp and insurance | CSLB says workers' compensation insurance is required by law if the contractor has employees or workers. Ask your attorney or insurer how an uninsured worker injury on your property could affect you. General liability insurance is generally meant to respond to damage caused by a contractor's work, but the specific terms of any policy vary. | Ask for a current certificate of workers' compensation insurance. CSLB says you can verify the policy on their website. General liability insurance is not required by CSLB, but CSLB says it is a good idea to ask about it. CSLB also suggests asking your own homeowner insurer whether a temporary rider is advisable during construction. | CSLB (workers' comp status); your insurer (temporary rider) | CSLB "Terms of Agreement" guide |
| Scope of work and exclusions | Defines exactly what the contractor will and will not do. In a total-loss rebuild, the boundary between site remediation or debris removal and the rebuild itself is a common source of confusion. Exclusions you did not notice become costs you did not budget for. | A written description of every phase and trade included. CSLB advises describing materials with specificity — brand, model, style, color, quantity — rather than a vague description such as "install maple cabinets." Look for a clear list of what is excluded: demolition, soil remediation, hazardous materials, landscaping, utility connections, fencing, driveways, and anything outside the building footprint. If your insurance estimate assumes certain work is included, check whether the proposal matches or excludes it. | Contractor (scope details); insurer (what the estimate assumes); building department (what requires a permit); architect or engineer (design questions) | CSLB "Terms of Agreement" guide (materials specificity); 1st Choice point of view (scope boundary and exclusion list) |
| Price structure | CSLB says the contract must state a fixed price for disaster-related rebuilds. This is intended to limit open-ended cost exposure, although the price can still change through a written change order. If the proposal says "cost plus" or "time and materials," ask why and verify with CSLB whether that is permitted for your project. | A single total contract price. If the contract breaks price into phases, the phase prices should add up to the total. Ask whether the price includes permit fees, plan-check fees, engineering, surveys, and utility connection fees — or whether those are separate. | CSLB (whether the pricing method is permitted); attorney (contract language) | CSLB Disaster Help Center; CSLB contract and payment sheet |
| Allowances and selections | An allowance is a dollar amount set aside in the contract for items you have not yet chosen — such as countertops, flooring, fixtures, or appliances. If your selections cost more than the allowance, you typically pay the difference. The contract should say whether the price is reduced if your selections cost less. Without clearly defined allowances, you cannot compare proposals or predict your actual costs. | A list of every allowance, the dollar amount, and what it covers. Ask what happens if you go over or under. Ask how the selection process works and what deadlines apply. Note: CSLB's consumer guide does not define "allowance." This explanation reflects common construction practice and is included as general guidance. | Contractor (allowance amounts and process); insurer (whether the insurance estimate includes comparable items); attorney (contract language) | 1st Choice point of view (allowance explanation as construction practice) |
| Payment schedule | Controls how money moves through the project. Payments tied to completed work protect you from paying for work that has not been done. CSLB says progress payments cannot exceed the value of work completed or materials delivered. | A written schedule showing each payment amount and the work or milestone that triggers it. Per CSLB guidance, the initial down payment is capped at $1,000 or ten percent of the contract price, whichever is the smaller amount. CSLB advises homeowners to avoid signing any contract or change order that requires a progress payment greater than the value of work already performed. When a contractor is unable to meet these requirements, CSLB recommends seeking bids from other contractors. | CSLB (payment limits); attorney (contract language); insurer (payment timing from the claim) | CSLB Disaster Help Center; CSLB "Terms of Agreement" guide; CSLB contract and payment sheet |
| Change orders | Rebuilds often uncover conditions that require changes — soil issues, code upgrades, or design revisions. Without a written change-order process, costs and schedule can shift without your approval. CSLB says the contract price can change only through a written change order that becomes part of the contract. | A written process requiring your signature before any change takes effect. Every change order should spell out what work is being added or modified, the dollar amount of the adjustment, and how the schedule and payment plan are affected. All changes must be documented in writing and signed by both parties. Ask an attorney to confirm the current legal requirements for change-order content. | Attorney (contract language); contractor (scope); insurer (whether the change affects the claim); building department (whether the change requires a revised permit) | CSLB "Terms of Agreement" guide |
| Permits and inspections | Rebuilding requires permits from your local building department. Inspections occur during and after construction. The contract should make clear who is responsible for pulling permits and whether the fees are included in the price. | A statement naming who pulls the permits and whether permit and plan-check fees are in the contract price. Ask about the inspection schedule — when inspections happen, who coordinates them, and how results are communicated to you. Permit and inspection requirements differ from one jurisdiction to the next. Confirm your specific requirements with the building department that has jurisdiction over your property. | Building department (permit requirements, plan review, inspections); contractor (coordination) | CSLB "Terms of Agreement" guide |
| Start and completion dates | Sets expectations for when work begins and when you can expect to move back in. Written dates give you a clearer basis for discussing delays. Ask an attorney how delay and default clauses would work in your contract. | Specific start and estimated completion dates. Ask what conditions could change them (permit delays, weather, material lead times, inspection holds, insurance payment timing). Ask whether the contract includes a notice-and-cure process for delays — meaning the contractor must notify you in writing, explain the cause, and state a revised date. | Contractor (schedule); attorney (delay and default clauses); building department (permit timeline) | CSLB "Terms of Agreement" guide (start and end dates); 1st Choice point of view (notice-and-cure process) |
| Communication and project-manager access | During a months-long rebuild, knowing who to call, how often you will receive updates, and how decisions are documented can help prevent miscommunication and dispute. | The name and contact information of your assigned project manager or primary point of contact. Ask how often you will receive written updates — weekly, biweekly, or at milestones. Ask how decisions and instructions are documented (email, project management software, written logs). | Contractor (communication plan) | 1st Choice point of view |
| Documentation and photos | Work behind walls — framing, rough plumbing, rough electrical, insulation, waterproofing — cannot be visually inspected once it is covered up. Dated photos and written records can help if questions arise later about what was installed or how it was done. | Ask whether the contractor provides dated jobsite photos at key phases. Ask what documentation you will receive and how it is stored. Ask specifically about documentation of work that will be concealed by drywall, stucco, or other finishes. | Contractor (documentation commitment); building department (inspection records) | 1st Choice point of view |
| Insurance interaction | Your rebuild contract is between you and your contractor. Your insurance claim is between you and your insurer. These are related but separate. The contract should not give the contractor control over your claim, and the contractor should not promise that insurance will cover specific work. | Ask how the contractor expects to be paid — directly by you, or through a process that involves the insurer. Ask whether the contract accounts for the possibility that insurance proceeds may arrive in stages (supplements) or may not cover the full contract price. Ask who is responsible for the difference if the contract price exceeds your insurance payout. Ask your insurer, not the contractor, about ordinance-or-law coverage, code-upgrade costs, and supplement timing. If your property has a mortgage, ask your lender whether they must approve disbursements. | Insurer (coverage, supplements, payment timing, ordinance or law); mortgage lender (disbursement requirements); attorney (contract language); California Department of Insurance (complaints or coverage disputes) | 1st Choice point of view (separation of contract and claim); CSLB "Terms of Agreement" guide (general contract guidance) |
| Warranty | A warranty defines what the contractor will fix after the project is complete, what is covered, and for how long. CSLB says if a contractor offers a warranty, get it in writing. CSLB also says to request manufacturer warranties for products and equipment. | Written warranty terms stating which parts of the work are covered and for how long. Separate manufacturer warranties for major systems, equipment, and materials. Ask what the process is for making a warranty claim after move-in. CSLB notes that homeowners have four years to file a CSLB complaint about a faulty project, and that this deadline can be extended by warranties written into the contract. | Attorney (warranty language); CSLB (complaints about faulty work) | CSLB "Terms of Agreement" guide |
| Lien protection | If the contractor does not pay subcontractors or suppliers, those parties may have the right to record a mechanics lien against your property — even if you paid the contractor in full. CSLB says the contract must include a mechanics lien warning. | The required mechanics lien warning in the contract. Request a list identifying each subcontractor and supplier expected to work on the project, along with their anticipated start and completion dates. As each portion of work is finished and paid, ask for lien releases — also called lien waivers — from those subcontractors and suppliers. CSLB also suggests paying by joint check as an option. | Attorney (lien rights and releases); CSLB (complaints) | CSLB "Terms of Agreement" guide |
| Cancellation and termination | You need to understand your right to cancel and both parties' right to terminate if the project is not working. CSLB's consumer guide describes a right to cancel within three business days (five if the buyer is 65 or older) for certain home improvement contracts negotiated away from the contractor's place of business. | Ask whether the contract includes the required cancellation notice. Ask what happens if either party wants to terminate after work has started — what costs are owed, what work product belongs to you, and how disputes about partial payment are resolved. For disaster-specific contracts, ask your attorney or CSLB whether any special cancellation rules apply. | Attorney (termination and cancellation clauses); CSLB (cancellation rights) | CSLB "Terms of Agreement" guide |
| Closeout | Closeout is the process of finishing the project and handing it over to you. Without a written closeout process, punch-list items can linger, documents can go missing, and the final payment can become a point of dispute. | Ask for a defined closeout process that includes: a final walkthrough, a written punch list of items to be corrected, a timeline for completing punch-list items, final lien releases from all subcontractors and suppliers, copies of all passed inspection records, warranty documents, manufacturer manuals, and a certificate of occupancy or final approval from the building department. Ask when the final payment is due relative to these steps. | Building department (final inspection and certificate of occupancy); attorney (final payment conditions); contractor (closeout documents) | 1st Choice point of view (closeout process); CSLB "Terms of Agreement" guide (lien releases, warranty) |
Who Decides What: A Quick Reference
One of the most confusing parts of rebuilding after a wildfire is figuring out which questions go to which party. The contractor cannot tell you what your insurance covers. The insurer cannot tell you what the building department requires. Use this table to direct your questions to the right source.
| Party | What They Decide or Verify |
|---|---|
| Contractor | Scope of work, means and methods of construction, construction sequencing, subcontractor selection and coordination, jobsite documentation, schedule management, material procurement, and quality of workmanship. |
| Insurer | What your policy covers, claim payment amounts and timing, supplement requests and approvals, ordinance-or-law coverage questions, and depreciation or holdback amounts. Contact your insurer or the California Department of Insurance for coverage questions or disputes. |
| Building department (authority having jurisdiction) | Permit requirements for your specific parcel, plan review and approval, required inspections during and after construction, Title 24 energy requirements, zoning, setbacks, and certificate of occupancy or final approval. Requirements vary by city and county. Confirm yours with the building department that has jurisdiction over your property. |
| Attorney | Contract clauses that carry legal risk, lien rights and releases, dispute resolution terms, termination conditions, warranty enforceability, and any term you do not fully understand before signing. |
| Architect or engineer | Design, structural calculations, foundation engineering, geotechnical questions, and plan preparation for permit submittal. If your rebuild involves design changes from the original home, an architect or engineer may be required. |
| CSLB | License status, bond status, workers' compensation status, complaint history, and filing complaints about contractor performance or licensing. Use the CSLB Disaster Help Center for wildfire-specific guidance and complaints. |
How to Compare Two or More Rebuild Proposals
If you have received proposals from different contractors, comparing them can feel impossible when the scopes, formats, and terminology differ. A common mistake is comparing the bottom-line price before confirming that both proposals cover the same work. A lower price that excludes permit fees, site preparation, utility connections, or finish allowances may not actually be lower — it can simply move those costs to later change orders.
Step One: Normalize the Scopes
Before comparing price, make both proposals describe the same project. Use this method:
- List every item that Proposal A includes but Proposal B excludes, and vice versa.
- List every allowance in each proposal: what it covers, and the dollar amount.
- Identify any item your insurance estimate assumes is included that neither proposal covers.
- Ask each contractor to provide a revised proposal that covers the same scope, or to price the missing items as separate line items so you can add them for comparison.
Only after the scopes match should you compare the total price.
Side-by-Side Proposal Worksheet
Use this grid to organize your comparison. Fill in the details from each proposal you are reviewing.
| Review Item | Proposal A | Proposal B | Notes / Questions |
|---|---|---|---|
| Work included in scope | |||
| Work explicitly excluded | |||
| Allowance items and amounts | |||
| Who pulls permits; are fees included | |||
| Payment schedule vs. work completed | |||
| Inspection and documentation commitments | |||
| Warranty terms (workmanship and manufacturer) | |||
| Items assumed by insurance estimate but missing from proposal | |||
| Items in proposal but not in insurance estimate | |||
| Change-order process described in writing | |||
| Named point of contact / project manager | |||
| Start and completion dates | |||
| Lien-release process described |
CSLB's older "Fast Facts: Rebuilding After a Disaster" publication recommends getting at least three bids from licensed contractors and says not to automatically take the lowest bid if it is far below the others. It also suggests asking to see the pocket license and photo ID, getting references, and viewing prior work.
Where the Contract Meets the Build: Why Verification Points Matter
This section reflects 1st Choice Development's point of view on how contract language connects to the physical construction process. It is not a CSLB requirement. Inspections are performed by the building department, and approvals are not controlled by the contractor.
A contract describes work on paper. The build is what actually happens on the jobsite. The gap between the two is where problems hide — especially the kind of problems that get sealed behind drywall, stucco, or concrete and cannot be seen once the next phase begins.
At 1st Choice Development, we manage each rebuild as a controlled construction operation with tracked and documented phases. We believe homeowners benefit when the contract names specific verification points where work is documented and confirmed before it is covered up. Here is why each matters:
- Site setup and grading: The lot must be properly prepared before any foundation work begins. Soil conditions, drainage, and grading affect the structural integrity of everything built above.
- Foundation: Foundation work is generally expected to match the approved plans and pass the required inspection before framing starts. Once concrete is poured and framing goes up, the foundation is no longer visible. Your building department determines which inspections apply.
- Framing: Structural framing defines the skeleton of the house. Framing inspections are intended to verify that the structure matches the approved plans before anything is enclosed.
- Rough MEP (mechanical, electrical, plumbing): These systems run through walls, floors, and ceilings. Rough inspections typically happen before insulation and drywall. After drywall is installed, you cannot see what is behind it without cutting into the wall.
- Title 24 energy compliance: California's energy code affects insulation, windows, HVAC, lighting, and other systems. Documentation and verification requirements vary by project and jurisdiction — confirm the specifics with your building department and your contractor's design team.
- Waterproofing: Waterproofing protects the structure from moisture damage. Flashing, weather barriers, and drainage details need to be installed correctly and documented before exterior finishes cover them.
- Finishes: Interior and exterior finishes are what you see and live with. This is where your allowance selections become reality. Quality control at this stage affects both appearance and durability.
- Testing and final inspections: Systems testing (which may include plumbing pressure tests, HVAC commissioning, and electrical testing) and final building department inspections are the steps used to determine whether the work meets requirements. Required tests and inspections vary by project and jurisdiction.
- Warranties and owner orientation: At project completion, you should receive all warranty documents, manufacturer manuals, inspection records, and a walkthrough of your finished home — including how systems work, what maintenance is required, and how to make a warranty claim.
When you review a contract, consider asking whether these kinds of verification points are named in the agreement. A contract that ties payments, documentation, and communication to completed and verifiable work gives you more visibility into what is happening at each stage — and more confidence that the work behind your walls was done correctly.
Which Contract Clauses Should an Attorney Review
Not every homeowner hires a construction attorney, but if you are signing a contract for a total-loss rebuild, an attorney's review can be worth the cost. The following clauses are where the most significant financial and legal risk tends to concentrate:
- Payment terms — to confirm they comply with current California law and that no payment exceeds the value of work completed
- Change-order process — to confirm that changes require your written approval and clearly state the cost and schedule impact
- Termination provisions — to understand what happens if you or the contractor want to end the agreement, what costs are owed, and what work product you retain
- Dispute resolution — to understand whether disputes go to mediation, arbitration, or court, and whether you are waiving any rights
- Lien provisions — to confirm lien-release requirements protect your property
- Warranty scope and limitations — to understand what is actually covered, for how long, and under what conditions
- Insurance-related language — to confirm the contract does not give the contractor control over your claim proceeds or make assumptions about what your policy will pay
- Indemnification and liability clauses — to understand what risks you are accepting
- Any clause you do not fully understand
This is not legal advice. It is a list of areas where legal review is commonly valuable. An attorney licensed in California can evaluate the specific language in your contract.
How Ordinance-or-Law Coverage Affects Your Contract
When a home is destroyed, current building codes may require upgrades that did not exist when the original home was built. Code-required changes can affect the foundation, framing, energy systems (Title 24), fire-resistant materials, electrical panels, plumbing, and accessibility features. These upgrades cost money that your base dwelling coverage may not fully address.
Some homeowner policies include a separate coverage called ordinance or law coverage (sometimes called "code upgrade coverage") that may help pay for code-required changes. Whether your policy includes this coverage, how much it provides, and what it applies to are questions only your insurer can answer. The contractor cannot tell you what your policy covers.
What this means for your contract:
- Ask your insurer whether you have ordinance-or-law coverage and what amount is available.
- Ask your contractor whether the contract price includes code-required upgrades or whether those would be handled through change orders.
- If the contract price exceeds your total insurance payout (dwelling coverage plus any ordinance-or-law coverage and supplements), understand in writing who is responsible for the difference.
- If you have questions or disputes about coverage, contact the California Department of Insurance.
What Closeout Documents Should You Receive
When the rebuild is complete, you should receive a set of closeout documents that protect you going forward. Ask for these in writing before you sign the contract, so the expectation is set from the beginning:
- Certificate of occupancy or final approval from the building department
- All passed inspection records
- Final lien releases from all subcontractors and material suppliers
- Written warranties — both the contractor's workmanship warranty and all manufacturer warranties for equipment, appliances, and materials
- Maintenance instructions for major systems (HVAC, plumbing, roofing, waterproofing)
- As-built drawings or plans, if applicable
- A completed punch list showing all items addressed
- Keys, garage remotes, security codes, and any system access credentials
Frequently Asked Questions
Does a wildfire rebuild contract need to be in writing?
Yes. The CSLB "Terms of Agreement" consumer guide states that California home improvement contracts over $500 (labor and materials combined) must be in writing and include specific consumer-rights information. A total-loss rebuild will exceed this threshold. Changes to the contract must also be in writing.
Can my rebuild contractor use a cost-plus or time-and-materials contract?
CSLB says contractors must use a fixed-price contract for disaster-related home improvement work, and that time-and-materials and cost-plus contracts are not allowed for this work. If a contractor proposes a different pricing structure, ask them to explain why and verify with CSLB whether it is permitted for your project.
How much can a contractor ask for as a down payment?
CSLB says the down payment for home improvement work cannot exceed $1,000 or 10 percent of the contract price, whichever is less. For a total-loss rebuild priced above $10,000, the arithmetic means the cap is $1,000, based on CSLB's stated rule. Verify the current limit with CSLB, as a small number of contractors with a qualifying bond on file may be exempt.
What if my insurance payout does not cover the full contract price?
The contract should address this in writing. Ask your insurer about remaining coverage, supplement possibilities, and ordinance-or-law coverage. Ask your contractor whether the contract price can be adjusted if the scope changes. Ask your attorney how the gap should be handled in the contract language. Do not assume insurance will automatically cover the full cost. If you have a mortgage, your lender may also need to approve disbursements.
Should I have an attorney review my rebuild contract?
An attorney review is not legally required, but it is commonly recommended for a project of this size and complexity. At minimum, consider having an attorney review the payment terms, change-order process, termination clause, dispute resolution clause, lien provisions, warranty terms, and any language related to insurance proceeds.
How do I file a complaint about a rebuild contractor in California?
CSLB offers a complaint route specifically for wildfire rebuilding through its Disaster Help Center. Within that portal, homeowners can submit complaints about hired contractors under the licensed and unlicensed project complaints category. You can also report a contractor working at a job site if you have concerns about licensing or workers' compensation coverage.
Start Your Rebuild on Solid Ground
Reviewing a rebuild contract takes time and careful attention, and that can feel like one more burden when you are already dealing with the aftermath of a wildfire. But the contract is one of the most important documents governing your money, your schedule, and the quality of your home for years to come. It is worth getting right.
At 1st Choice Development, we work with homeowners in Altadena and Pacific Palisades who are rebuilding after wildfire. Our approach is built on documented phases, clear communication, inspection readiness, and one accountable process from pre-construction through final handoff. We believe a good contract reflects a good process — and that homeowners deserve to understand both before they sign.
Schedule a rebuild consultation with 1st Choice Development to discuss your project, your questions, and what a clear, documented rebuild process looks like for your property.
Questions about your rebuild?
We rebuild fire-damaged homes across Altadena and Pacific Palisades, and we are happy to talk through your situation.
Talk to us